Project Update

Jakarta MRT North-South Line Phase I (Lebak Bulus – Bundaran HI, Operational 2016)

Basic Design (14 month)
Commencement date November 23, 2009
Basic Engineering Design has been completed  (January 23, 2011)
Tender pre-qualifications of construction to start in April 2011
Tender of construction to start in 2011

Land Acquisition
Acquisition of land, executed by agencies within DKI Jakarta Provincial Government, is targeted to be completed before start of construction works.

Procurement of Tender Assistance Consultants done by PT MRT Jakarta, has obtained selected Consultant. Notice to proceed is to be published
soon.

Recommendation of Environment Impact Assessment (EIA) has been published by Environmental Management Agency of DKI Jakarta (BPLHD) on November 18th, 2010 through recommendation letter Number  51/Andal/-1.774.151.

Prequalification tender for Surface Section and Undeground Section have been opened  on 15th April 2011 and result notification have been announced on 8th December 2011 . For more information please click here

 

Jakarta MRT North-South Line Phase II (Bundaran HI – Kp. Bandan, Operational 2018)

Feasibility Study under Japanese grant has been completed
At present, finalization of EIA is being processed. Funding commitment from JICA is targeted to be obtained in 2011
Basic Design Works to start one year after funding commitment.
Operations to start in 2018

Recommendation of Environment Impact Assessment (EIA) has been published by Environmental Management Agency of DKI Jakarta (BPLHD) on January 28th, 2011 through recommendation letter number 06/Andal/-1.774.151

 

Jakarta MRT East-West Line (Alternative Route: Balaraja – Cikarang)

Feasibility Study works under Japanese grant has been started in April 2011